3 Waters pipe renewals

Over the next year, the Dunedin City Council will be renewing water, stormwater and wastewater pipes in several parts of Dunedin to improve the quality of the city’s infrastructure, reduce overflows and improve water supply fire flows.

This project includes work in Mornington, Maori Hill, North Dunedin and Dunedin Central.

Overall, work will start in December 2018 and run until around September 2019. Residents will be advised of the specific dates for each area. The project will include some work in private properties.

  • Cochrane / Haywood Street area, Mornington

    We are replacing almost 1.5km of pipes in the Cochrane/Haywood Street area. We will be replacing water and wastewater pipes on the road on Cochrane Street and will replace wastewater and stormwater pipes on some private properties. We are aiming to start work in this area in January 2019 and to complete it in the second half of the year.

    The pipes in the Cochrane/Haywood Street area, like those in many parts of the city, are old and do not perform well. The pipes are up to 100 years old and have begun to deteriorate.

    The project will:

    • renew infrastructure that has reached the end of its life
    • reduce the risk of wastewater overflows caused by stormwater and groundwater getting into our wastewater network and by wastewater getting into our stormwater network
    • reduce the risk of wastewater contaminating watercourses and private property
    • improve water supply fire flows to current standards.

    Extent of work in the Cochrane / Haywood Street area, Mornington
    Extent of work in the Cochrane / Haywood Street area, Mornington

  • Hawthorn Avenue

    We are replacing wastewater pipes on Hawthorn Avenue. Some work may be done on private property. We are aiming to do the work in this area from November to December this year, but will confirm the timing once we have awarded the contract.

    The pipes on Hawthorn Avenue, like those in many parts of the city, are old and do not perform well. The pipes are up to 100 years old and have begun to deteriorate.

    The project will:

    • renew infrastructure that has reached the end of its life
    • reduce the risk of wastewater overflows caused by stormwater and groundwater getting into our wastewater network
    • reduce the risk of wastewater contaminating watercourses and private property.

    Extent of work in Hawthorn Avenue, Mornington
    Extent of work in Hawthorn Avenue, Mornington

  • Claremont Street, Maori Hill

    We are replacing wastewater pipes on Claremont Street, including some work on private properties. Work in this area will be done in December 2018.

    The pipes on Claremont Street, like those in many parts of the city, are old and do not perform well. The pipes are up to 100 years old and have begun to deteriorate.

    The project will:

    • renew infrastructure that has reached the end of its life
    • reduce the risk of wastewater overflows caused by stormwater and groundwater getting into our wastewater network
    • reduce the risk of wastewater contaminating watercourses and private property.

    Extent of work in Claremont Street, Maori Hill

    Extent of work in Claremont Street, Maori Hill

  • Canongate area, Dunedin Central

    We are replacing water and wastewater pipes in the Canongate area. Some work may be done on private property. We are aiming to do the work in this area from December to February, but will confirm the timing once we have awarded the contract.

    The pipes in the Canongate area, like those in many parts of the city, are old and do not perform well. The pipes are up to 100 years old and have begun to deteriorate.

    The project will:

    • renew infrastructure that has reached the end of its life
    • reduce the risk of wastewater overflows caused by stormwater and groundwater getting into our wastewater network
    • reduce the risk of wastewater contaminating watercourses and private property
    • improve water supply fire flows to current standards.

    Extent of work in the Canongate area, Dunedin Central
    Extent of work in the Canongate area, Dunedin Central

  • Union Place, North Dunedin

    We are replacing wastewater pipes on Union Place, between Cumberland Street and Leith Walk. We are aiming to do the work in this area from October to November this year, but will confirm the timing once we have awarded the contract.

    The pipes on Union Place, like those in many parts of the city, are old and do not perform well. The pipes are up to 100 years old and have begun to deteriorate.

    The project will:

    • renew infrastructure that has reached the end of its life
    • reduce the risk of wastewater overflows caused by stormwater and groundwater getting into our wastewater network
    • reduce the risk of wastewater contaminating watercourses and private property.

    Extent of work in Union Place, North Dunedin
    Extent of work in Union Place, North Dunedin