Building owners are being encouraged to stay informed about pending changes to the national earthquake-prone building (EPB) system which will have implications for Dunedin.

Parliament recently passed the Building (Earthquake-prone Buildings) Amendment Act 2026, which changed parts of Dunedin and coastal Otago from a low-risk seismic zone to a medium-risk zone.

The change in seismic risk classification came into effect immediately, on 26 September 2026, while other changes introduced by the Act will come into force from 1 July 2027.

Dunedin City Council Acting Building Services Manager Mike Hart says the legislation introduces a more targeted, risk-based approach to earthquake-prone buildings.

From 1 July 2027, only unreinforced masonry buildings and buildings three storeys or taller made of heavy materials can be classified as earthquake-prone.

Requirements for those buildings will depend on the type of building and its circumstances, but will range from remaining on the EPB register and displaying an EPB sign, through to façade work or a more extensive retrofit.

The Ministry of Business, Innovation and Employment (MBIE) is consulting on the proposed EPB methodology, guidance, and other technical information, which will provide further guidance once finalised, Mr Hart says.

From 1 July 2027, buildings will also no longer be required to have a New Building Standard (%NBS) rating. If building owners undertake voluntary engineering assessments, a result below 34%NBS will no longer, by itself, result in a building being classified as earthquake-prone.

Dunedin currently has 483 buildings recorded as earthquake-prone, while approximately 3,334 buildings considered potentially earthquake-prone are still to be assessed.

DCC staff will review buildings already on Dunedin’s register to determine which remain within the new system and what requirements will apply, Mr Hart says. The new legislation requires buildings already listed as earthquake-prone to be reviewed by 30 September 2027, while those considered potentially earthquake-prone must be assessed by 1 July 2032.

“Buildings already identified as earthquake-prone will be reviewed against the new legislative criteria. If they continue to meet the definition of an earthquake-prone building, the existing remediation timeframe of 35 years will remain unchanged.

“However, buildings newly identified as earthquake-prone under the revised system will generally have a 25-year timeframe within which to complete the required risk-remediation work.”

Building owners can apply to the Dunedin City Council for extensions to complete seismic work of up to a cumulative total of 15 years, Mr Hart says.

In the meantime, building owners should continue to comply with existing requirements and deadlines that apply to their buildings, and stay informed about developments.

“Once the new rules are in force from 1 July 2027, we’ll begin contacting building owners as we work through the reviews.

“It's important to note that a building no longer being classified as earthquake-prone does not mean it is free from seismic risk. In many cases, the focus of the new approach is on addressing risks to public safety, such as preventing parts of a building facade from falling onto public spaces.

“Building owners may still choose to undertake additional strengthening work to improve the performance of the building itself and enhance the safety of occupants.”

Further information: Changes to the earthquake-prone building system | Building Performance

MBIE consultation: Consultation on the Earthquake-prone Building Legislation and Methodology Guidance and Technical Annexes | Ministry of Business, Innovation & Employment

DCC contact: Earthquake-Prone Building Officer
Phone:   03 477 4000
Email: earthquakepronebuildings@dcc.govt.nz

Still didn't find what you were looking for?