Courses of action and possible projects

Focus on Safety
Courses of action Status
Road Safety Action Planning On-going
Risk targeting On-going
Focussing on vulnerable users On-going
Implementing safe speeds To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
Schools:
Top 12 schools programme. On-going
School Traffic Safety Group On-going
Road safety campaigns On-going
Possible interventions that could address key problems and opportunities under ‘Focus on Safety’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5).
CC. Central City and North Dunedin safety and accessibility upgrade Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
PH. Portobello/Harington Point Road Improvements Underway
SH. State Highway 1 (one-way pair) safety and accessibility investigation No funding allocated in 2012/13 – 2021/22 LTP
MC. Mosgiel centre safety and accessibility upgrade No funding allocated in 2012/13 – 2021/22 LTP
TP. Tertiary Precinct safety and accessibility upgrade Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
CN. Strategic Cycle Network Network planning underway
CU. Major centre upgrades No funding allocated in 2012/13 – 2021/22 LTP
ED. Road Safety Education On-going
PH. Pine Hill Road – Great King Street intersection NZTA project
SS. Safety upgrade of SH1 corridor south of Mosgiel (East Taieri area) NZTA projectP
SP. State Highway 88 shared path NZTA project
Focus on Travel Choices
Courses of action Status
Strategic Cycle Network:
South Dunedin Cycle Network (2013 – 2015) Underway. Funding allocated in 2012/13 – 2021/22 LTP
North and Central Dunedin Cycle Network (2015 – 2018) Network planning underway. $300,000 per annum in current LTP.
Other SCN routes (2018+) $300,000 per annum for duration of 2012/13 – 2021/22 LTP
Cycle parking On-going
Strategic Pedestrian Network On-going. To be implemented operationally.
Public Transport advocacy:
Advocating for improved public transport system On-going
Advocating for airport bus service To be investigated
Advocating for uptake of low-carbon bus technology To be investigated
Public transport governance investigation Underway
Protecting access to transport infrastructure (jetties, railway facilities). To be investigated
Support for travel choices:
Cycle-skills training Underway till 2014/15.
No funding allocated beyond 2014/15.
Bike library development Pilot project underway until June 2015. No funding allocated beyond 2014/15.
Work-place and school travel planning No funding allocated in 2012/13 – 2021/22 LTP
Walk and wheel days Sport Otago project, part funded by DCC from existing budgets on an on-going basis
Travel Smart programmes To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
Road user workshops On-going, from existing budgets
Bike Wise (annual event) Underway till 2014/15.
No funding allocated beyond 2014/15.
Walk to Work Day (annual event) Underway till 2014/15.
No funding allocated beyond 2014/15.
Dunedin Cycle Map publication On-going, from existing budgets
Possible interventions that could address key problems and opportunities under ‘Focus on Travel Choices’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5).
CC. Central City and North Dunedin safety and accessibility upgrade Early planning stages underway
MC. Mosgiel centre safety and accessibility upgrade No funding allocated in 2012/13 – 2021/22 LTP
TP. Tertiary Precinct safety and accessibility upgrade Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
CU. Major centre upgrades No funding allocated in 2012/13 – 2021/22 LTP
CN. Strategic Cycle Network Network planning underway
PH. Portobello/Harington Point Road Improvements Underway
SH. State Highway 1 (one-way pair) safety and accessibility investigation No funding allocated in 2012/13 – 2021/22 LTP
CH. City to Harbour bridge No funding allocated in 2012/13 – 2021/22 LTP
WP. Investigation of conversion of the one-way system to two-way south of Queens Gardens Funding for investigation stage included in operational budgets for 2013/14. No funding for implementation allocated in 2012/13 – 2021/22 LTP
ED. Road Safety Education On-going
SP. State Highway 88 shared path NZTA project
Focus on Centres
Courses of action Status
Integrating land use and transport:
District Plan Review (transport hierarchy and zoning provisions) Undearway
Central city safety and accessibility improvements. Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
Centres programme:
Mosgiel centre safety and accessibility improvements To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
Tertiary area safety and accessibility improvements Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
Other centres improvements To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. Some improvements to be carried out through operational programmes.
Parking Management Policy To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
Bylaw and policy reviews to align with Integrated Transport Strategy As and when they come up for review
Possible interventions that could address key problems and opportunities under ‘Focus on Centres’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5).
CC. Central City and North Dunedin safety and accessibility upgrade Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
MC. Mosgiel centre safety and accessibility upgrade No funding allocated in 2012/13 – 2021/22 LTP
TP. Tertiary Precinct safety and accessibility upgrade Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
CU. Major centre upgrades Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP
CN. Strategic Cycle Network Network planning underway
MR. Mosgiel residential growth transportation projects Underway
Focus on Freight
Courses of action Status
Freight on rail investigation To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
Strategic freight corridor identification:
Designated freight route upgrades To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
District Plan review (transport hierarchy and zoning provisions) Underway
Maintenance of critical infrastructure on HPMV routes and protection of over-dimension routes:
Operational – maintenance and renewals On-going
District Plan review (transport hierarchy and zoning provisions) Underway
Freight route congestion management, according to hierarchy of interventions On-going as required, through operational programmes.
Inland Port investigations and partnerships To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
Possible interventions that could address key problems and opportunities under ‘Focus on Freight’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5).
EB. Eastern Bypass Freight Route upgrade To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
FR. Freight by Rail study To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
PH. Pine Hill Road – Great King Street intersection NZTA project
SS. Safety upgrade of SH1 corridor south of Mosgiel (East Taieri area) To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
PM. Preventative Maintenance Strategy To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
ED. Road Safety Education On-going
SP. State Highway 88 shared path NZTA project
Focus on a Resilience
Courses of action Status
Supporting the Spatial Plan – Integrating land use and transport:
District Plan review – transport hierarchy and zoning provisions Underway
Provision of high quality people-centred urban public spaces e.g. urban gardens, pedestrian areas. To be investigated. No funding allocated in 2012/13 – 2021/22 LTP.
Supporting the Spatial Plan – resilience in rural areas:
District Plan review – transport hierarchy and zoning provisions Underway
Links to Energy Plan: exploring local alternative fuel development and other ways of strengthening rural transport resilience. To be investigated through Energy Plan development.
Exploring funding mechanisms for local place-based transport initiatives. To be investigated through Energy Plan development.
Links to Environment Strategy:
Emissions reduction targets To be investigated through Environment Strategy development.
Dunedin Digital Strategy Underway. Implemented through the Economic Development Strategy.
DCC internal initiatives:
Explore DCC vehicle fleet fuel efficiency improvements To be investigated. No funding allocated in 2012/13 – 2021/22 LTP.
Develop DCC work place travel plan To be investigated. No funding allocated in 2012/13 – 2021/22 LTP.
Investigate Economic Network Model To be investigated. No funding allocated in 2012/13 – 2021/22 LTP.
Explore and support alternatives to bitumen and recycling of roading waste (including possible links with Waste Minimisation Plan – Waste Levy Fund) To be investigated. No funding allocated in 2012/13 – 2021/22 LTP.
Possible interventions that could address key problems and opportunities under ‘Focus on Resilience’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5).
PM. Preventative Maintenance Strategy To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
FR. Freight by Rail study To be investigated. No funding allocated in 2012/13 – 2021/22 LTP
CN. Strategic Cycle Network Network planning underway
CC. Central City and North Dunedin safety and accessibility upgrade Underway, early planning stages. No funding allocated in 2012/13 – 2021/22 LTP
CU. Major centre upgrades No funding allocated in 2012/13 – 2021/22 LTP
MC. Mosgiel centre safety and accessibility upgrade No funding allocated in 2012/13 – 2021/22 LTP
PH. Portobello/Harington Point Road Improvements Underway
CH. City to Harbour bridge No funding allocated in 2012/13 – 2021/22 LTP
WP. Investigation of conversion of the one-way system to two-way south of Queens Gardens No funding allocated in 2012/13 – 2021/22 LTP
SP. State Highway 88 shared path NZTA project
General Actions
Courses of action Status
Integrated Transport Strategy Monitoring Plan:
Develop Monitoring Plan To be investigated. Existing budgets.
Review Transportation Activity Management Plan and Annual Plan indicators to align with Integrated Transport Strategy. To be investigated. Existing budgets.
Network Operating Plan development Underway. Existing budgets.
Transportation Operations and other DCC departments to review practices to align with Integrated Transport Strategy On-going once Integrated Transport Strategy is adopted by Council