| Focus on Safety |
| Courses of action |
Status |
| Road Safety Action Planning |
On-going |
| Risk targeting |
On-going |
| Focussing on vulnerable users |
On-going |
| Implementing safe speeds |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| Schools: |
| Top 12 schools programme. |
On-going |
| School Traffic Safety Group |
On-going |
| Road safety campaigns |
On-going |
| Possible interventions that could address key problems and opportunities under ‘Focus on Safety’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5). |
| CC. Central City and North Dunedin safety and accessibility upgrade |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| PH. Portobello/Harington Point Road Improvements |
Underway |
| SH. State Highway 1 (one-way pair) safety and accessibility investigation |
No funding allocated in 2012/13 – 2021/22 LTP |
| MC. Mosgiel centre safety and accessibility upgrade |
No funding allocated in 2012/13 – 2021/22 LTP |
| TP. Tertiary Precinct safety and accessibility upgrade |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| CN. Strategic Cycle Network |
Network planning underway |
| CU. Major centre upgrades |
No funding allocated in 2012/13 – 2021/22 LTP |
| ED. Road Safety Education |
On-going |
| PH. Pine Hill Road – Great King Street intersection |
NZTA project |
| SS. Safety upgrade of SH1 corridor south of Mosgiel (East Taieri area) |
NZTA project |
| SP. State Highway 88 shared path |
NZTA project |
| Focus on Travel Choices |
| Courses of action |
Status |
| Strategic Cycle Network: |
| South Dunedin Cycle Network (2013 – 2015) |
Underway. Funding allocated in 2012/13 – 2021/22 LTP |
| North and Central Dunedin Cycle Network (2015 – 2018) |
Network planning underway. $300,000 per annum in current LTP. |
| Other SCN routes (2018+) |
$300,000 per annum for duration of 2012/13 – 2021/22 LTP |
| Cycle parking |
On-going |
| Strategic Pedestrian Network |
On-going. To be implemented operationally. |
| Public Transport advocacy: |
| Advocating for improved public transport system |
On-going |
| Advocating for airport bus service |
To be investigated |
| Advocating for uptake of low-carbon bus technology |
To be investigated |
| Public transport governance investigation |
Underway |
| Protecting access to transport infrastructure (jetties, railway facilities). |
To be investigated |
| Support for travel choices: |
| Cycle-skills training |
Underway till 2014/15.
No funding allocated beyond 2014/15. |
| Bike library development |
Pilot project underway until June 2015. No funding allocated beyond 2014/15. |
| Work-place and school travel planning |
No funding allocated in 2012/13 – 2021/22 LTP |
| Walk and wheel days |
Sport Otago project, part funded by DCC from existing budgets on an on-going basis |
| Travel Smart programmes |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| Road user workshops |
On-going, from existing budgets |
| Bike Wise (annual event) |
Underway till 2014/15.
No funding allocated beyond 2014/15. |
| Walk to Work Day (annual event) |
Underway till 2014/15.
No funding allocated beyond 2014/15. |
| Dunedin Cycle Map publication |
On-going, from existing budgets |
| Possible interventions that could address key problems and opportunities under ‘Focus on Travel Choices’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5). |
| CC. Central City and North Dunedin safety and accessibility upgrade |
Early planning stages underway |
| MC. Mosgiel centre safety and accessibility upgrade |
No funding allocated in 2012/13 – 2021/22 LTP |
| TP. Tertiary Precinct safety and accessibility upgrade |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| CU. Major centre upgrades |
No funding allocated in 2012/13 – 2021/22 LTP |
| CN. Strategic Cycle Network |
Network planning underway |
| PH. Portobello/Harington Point Road Improvements |
Underway |
| SH. State Highway 1 (one-way pair) safety and accessibility investigation |
No funding allocated in 2012/13 – 2021/22 LTP |
| CH. City to Harbour bridge |
No funding allocated in 2012/13 – 2021/22 LTP |
| WP. Investigation of conversion of the one-way system to two-way south of Queens Gardens |
Funding for investigation stage included in operational budgets for 2013/14. No funding for implementation allocated in 2012/13 – 2021/22 LTP |
| ED. Road Safety Education |
On-going |
| SP. State Highway 88 shared path |
NZTA project |
| Focus on Centres |
| Courses of action |
Status |
| Integrating land use and transport: |
| District Plan Review (transport hierarchy and zoning provisions) |
Underway |
| Central city safety and accessibility improvements. |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| Centres programme: |
| Mosgiel centre safety and accessibility improvements |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| Tertiary area safety and accessibility improvements |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| Other centres improvements |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. Some improvements to be carried out through operational programmes. |
| Parking Management Policy |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| Bylaw and policy reviews to align with Integrated Transport Strategy |
As and when they come up for review |
| Possible interventions that could address key problems and opportunities under ‘Focus on Centres’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5). |
| CC. Central City and North Dunedin safety and accessibility upgrade |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| MC. Mosgiel centre safety and accessibility upgrade |
No funding allocated in 2012/13 – 2021/22 LTP |
| TP. Tertiary Precinct safety and accessibility upgrade |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| CU. Major centre upgrades |
Early planning stages underway. No funding allocated in 2012/13 – 2021/22 LTP |
| CN. Strategic Cycle Network |
Network planning underway |
| MR. Mosgiel residential growth transportation projects |
Underway |
| Focus on Freight |
| Courses of action |
Status |
| Freight on rail investigation |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| Strategic freight corridor identification: |
| Designated freight route upgrades |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| District Plan review (transport hierarchy and zoning provisions) |
Underway |
| Maintenance of critical infrastructure on HPMV routes and protection of over-dimension routes: |
| Operational – maintenance and renewals |
On-going |
| District Plan review (transport hierarchy and zoning provisions) |
Underway |
| Freight route congestion management, according to hierarchy of interventions |
On-going as required, through operational programmes. |
| Inland Port investigations and partnerships |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| Possible interventions that could address key problems and opportunities under ‘Focus on Freight’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5). |
| EB. Eastern Bypass Freight Route upgrade |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| FR. Freight by Rail study |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| PH. Pine Hill Road – Great King Street intersection |
NZTA project |
| SS. Safety upgrade of SH1 corridor south of Mosgiel (East Taieri area) |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| PM. Preventative Maintenance Strategy |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| ED. Road Safety Education |
On-going |
| SP. State Highway 88 shared path |
NZTA project |
| Focus on a Resilience |
| Courses of action |
Status |
| Supporting the Spatial Plan – Integrating land use and transport: |
| District Plan review – transport hierarchy and zoning provisions |
Underway |
| Provision of high quality people-centred urban public spaces e.g. urban gardens, pedestrian areas. |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. |
| Supporting the Spatial Plan – resilience in rural areas: |
| District Plan review – transport hierarchy and zoning provisions |
Underway |
| Links to Energy Plan: exploring local alternative fuel development and other ways of strengthening rural transport resilience. |
To be investigated through Energy Plan development. |
| Exploring funding mechanisms for local place-based transport initiatives. |
To be investigated through Energy Plan development. |
| Links to Environment Strategy: |
| Emissions reduction targets |
To be investigated through Environment Strategy development. |
| Dunedin Digital Strategy |
Underway. Implemented through the Economic Development Strategy. |
| DCC internal initiatives: |
| Explore DCC vehicle fleet fuel efficiency improvements |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. |
| Develop DCC work place travel plan |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. |
| Investigate Economic Network Model |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. |
| Explore and support alternatives to bitumen and recycling of roading waste (including possible links with Waste Minimisation Plan – Waste Levy Fund) |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP. |
| Possible interventions that could address key problems and opportunities under ‘Focus on Resilience’ (to be assessed through a Programme Business Case, see Sections 9.1 and 9.5). |
| PM. Preventative Maintenance Strategy |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| FR. Freight by Rail study |
To be investigated. No funding allocated in 2012/13 – 2021/22 LTP |
| CN. Strategic Cycle Network |
Network planning underway |
| CC. Central City and North Dunedin safety and accessibility upgrade |
Underway, early planning stages. No funding allocated in 2012/13 – 2021/22 LTP |
| CU. Major centre upgrades |
No funding allocated in 2012/13 – 2021/22 LTP |
| MC. Mosgiel centre safety and accessibility upgrade |
No funding allocated in 2012/13 – 2021/22 LTP |
| PH. Portobello/Harington Point Road Improvements |
Underway |
| CH. City to Harbour bridge |
No funding allocated in 2012/13 – 2021/22 LTP |
| WP. Investigation of conversion of the one-way system to two-way south of Queens Gardens |
No funding allocated in 2012/13 – 2021/22 LTP |
| SP. State Highway 88 shared path |
NZTA project |