Financial update

Financial update

Council’s capital programme includes an estimated spend of $240 million in the 2026/27 year, which is higher than the $230 million planned for that year in the long‑term budget.

The 3 Waters component of the 2026/27 programme is $92 million, which is not expected to change. Council is currently reviewing the remaining ‘non‑waters’ component of $148 million.

Current‑year delivery performance is an important consideration in shaping the 2026/27 capital programme. The current‑year ‘non-waters’ programme is tracking behind schedule, with several projects experiencing delays for a variety of reasons. As a result, Council has rephased some work into 2026/27.

We are still fine‑tuning the 2026/27 plan, because experience shows we can realistically deliver a combined total of about $200 million of 3 Waters and ‘non-waters’ projects. Council will review a budget update in May 2026.

Forecast debt levels are lower than indicated in the 9 Year Plan mainly due to the current-year delays in the capital programme delivery.

The draft Annual Plan provides a balanced budget in ‘non-waters’ activities. As forecast in the 9 Year Plan and Council’s Water Services Delivery Plan, 3 Waters activities will achieve a balanced budget in the 2027/28 year.

Stadium funding

Last year, the 9 Year Plan 2025-34 increased annual funding to the Stadium by $2 million to support event attraction at the Forsyth Barr Stadium and Dunedin Centre Town Hall ($1.645 million) and to service debt held by the company that owns the stadium, Dunedin Stadium Property Ltd (DSPL), ($0.355 million). This raised the total annual funding to DSPL for capital expenditure and debt repayment to $2.905 million.

Council asked for an updated DSPL debt repayment plan for consideration during this 2026/27 draft Annual Plan process.

We propose additional funding from rates, for maintenance, to enable debt repayment and support the long-term financial sustainability. Funding would increase by $1.25 million in 2026/27 (bringing the total payment to $4.155 million), and then rise by an additional $1.25 million from 2027/28 onwards (bringing the total annual payment to $5.405 million).

Rating Method

Reports to Council

Reports to the 4-5 March 2026 Council meeting

Finances - All of Council

Finances - by Activities

The financial statements and reports are listed for each Activity

Still didn't find what you were looking for?